- RESILIENCE-MESH supplementary scope: learning how real household devices behave, safe rollout limits, and the "opposite" use case (fire: turn systems ON)
- 1. Why this document exists
- 2. Scope boundary (what the mesh is and is not)
- 3. Device Characterisation Programme ("learn how household devices actually work")
- 4. Testing Bounds: staged rollout with explicit limits
- 5. Bidirectional crisis modes
- 6. Per-device safe-default matrix (to be filled by the 3.2 programme)
- 7. Public participation and trust
- 8. Governance, legal and risk
- 9. Proposed additions to the funding request (feeds doc 06)
- 10. Open questions to resolve with experts
08. Adaptive Testing Bounds & Bidirectional Crisis Modes
RESILIENCE-MESH supplementary scope: learning how real household devices behave, safe rollout limits, and the "opposite" use case (fire: turn systems ON)
Status: DRAFT for review. Not yet audited. Device behaviours, agency policy positions and fire-science claims below are working assumptions to be verified with primary sources (DFES / DWER / Water Corporation / manufacturers) before submission.
1. Why this document exists
Documents 01-06 frame RESILIENCE-MESH mainly as restriction: curtail irrigation and non-essential load in drought or grid stress. Real crises are bidirectional:
| Crisis | Water side | Power / solar side |
|---|---|---|
| Severe drought / reservoir stress | Reduce non-potable irrigation | Reduce peak demand, shift load |
| Grid stress / minimum demand | n/a | Curtail export, absorb surplus (load up) |
| Bushfire approaching | Increase wetting of defined zones, if pressure and policy allow | Keep pumps powered; manage inverter/battery fire hazards; protect responder safety |
| Storm / blackout | Preserve reserve | Island, prioritise critical loads |
A framework that can only say "off" is incomplete and, in a fire, potentially harmful. The mesh must carry signed commands in both directions, with the same safety governor, and must learn and bound what each class of household device can actually do before being trusted with either direction.
2. Scope boundary (what the mesh is and is not)
Is: an opt-in, signed, geo-scoped, time-limited coordination layer for non-potable irrigation controllers, pumps, valves, and DER (solar/battery) that already exist at homes, farms and councils.
Is not: - A substitute for evacuation advice, emergency services, or fire authorities' decisions. - A claim that sprinklers will save a home. Evidence on residential sprinkler effectiveness in bushfire is mixed; the mesh must not create false confidence. Participation messaging must say so. - Covert control. All control is consented, logged and visible to the owner.
3. Device Characterisation Programme ("learn how household devices actually work")
Before any rollout, build an empirical device catalogue: how each device class responds to commands, loses connectivity, reboots, and fails.
3.1 Device classes to characterise
- Wi-Fi / app hose-tap and garden timers (e.g. Tuya-platform and Gardena-style devices).
- Smart irrigation controllers with cloud + local APIs (e.g. Rachio, Hunter Hydrawise, Rain Bird-class products).
- Generic Wi-Fi / Zigbee / Matter relays and smart plugs switching pumps or solenoids (e.g. Shelly-class).
- Bore/rainwater/tank pumps and pressure controllers (including variable-speed).
- Pool pumps (large flexible load, relevant for both water and power).
- Solar inverters / batteries (Sungrow, Fronius, GoodWe, Solis, Sigenergy; see the interface research report).
- Municipal-scale: council irrigation controllers, SCADA-fed valves.
- Legacy "dumb" timers (cannot be controlled; mesh must treat as unmanaged and model their load).
3.2 What to measure for every device model
| Attribute | Question |
|---|---|
| Command path | Local LAN, cloud-only, BLE, 433 MHz, wired? |
| Latency | Command to physical effect (p50/p95/p99) |
| Offline behaviour | If Wi-Fi/cloud drops mid-run: stays on, stays off, or reverts to schedule? (Critical: a valve stuck open or closed.) |
| Power-loss behaviour | State after brownout/reboot |
| Schedule precedence | Do local schedules, rain delays, or app overrides beat remote commands? |
| Command acknowledgement | Does it confirm actuation, or just accept the message? |
| Authentication / security | Tokens, local auth, firmware update model |
| Rate limits / ToS | API quotas, terms restricting automation |
| Failure modes | Stuck states, duplicate commands, clock drift |
| Hydraulic effect | Flow (L/min), pressure drop at the tap, effect on neighbours |
| Electrical effect | Inrush, running power, interaction with solar/battery |
Output: a versioned Device Behaviour Matrix and a conformance test each device must pass to be "mesh-ready at level N".
3.3 Capability levels
- L0 Observed: telemetry only.
- L1 Advisory: notifies the owner; owner acts.
- L2 Bounded control: mesh may command within hard caps, auto-revert proven.
- L3 Emergency eligible: passed fail-safe, offline, and acknowledgement tests; may act on signed crisis commands.
Only L3 devices can receive crisis commands. Unknown or failed devices stay L0/L1.
4. Testing Bounds: staged rollout with explicit limits
Each stage has entry criteria, hard bounds, and abort criteria. No stage starts without the previous passing and being signed off by the safety/ethics reviewer.
| Stage | Environment | Max scope | Hard bounds | Abort / rollback triggers |
|---|---|---|---|---|
| S0 Simulation | Digital twin of a suburb: hydraulics (pressure/flow), electrical feeder, device models from 3.2 | Unlimited | n/a | n/a (learning) |
| S1 Bench / lab | Real devices on a test rig with metered water and mains | 1 of each device class | Isolated water supply, RCD-protected | Any stuck valve, unexpected state |
| S2 Researcher homes | Team's own properties + informed staff | ~5-10 sites | Owner can override instantly; max run-time per command; non-potable only | Any owner complaint, any hydraulic anomaly |
| S3 Volunteer pilot | Informed, consenting households with signed participation terms | ~50-200 sites, one distribution zone | Pressure floor monitored at zone boundary; command rate capped; TTL <= minutes | Zone pressure below floor, device failure rate above threshold, cyber alert |
| S4 Drill / exercise | Scheduled, announced "crisis drill" with utility and emergency services | One suburb | Drill commands are flagged as drill; real-emergency override always wins | Same as S3 + operations centre veto |
| S5 Regional readiness | Multi-suburb, still opt-in | Expanded | Formal sign-off by utility, emergency authority, regulator | Standing abort authority |
4.1 Hard bounds that apply everywhere
- Pressure floor: mesh never commands load that could push the local water network below the utility-defined floor needed for firefighting and potable supply.
- Rate limiting / staggering: commands are spread over time (jittered) so thousands of devices never switch simultaneously (avoids pressure transients and electrical inrush).
- TTL and dead-man: every command expires; loss of heartbeat reverts to the device's safe default (defined per device class, see section 6).
- Max-duration per household per window (prevents tank/bore exhaustion and flooding).
- Potable/medical/life-support lines are physically out of scope.
- Human-in-the-loop for step-ups: escalation between levels needs authenticated human authorisation, not just an algorithm.
4.2 Learning loop (how rollout "learns")
- Log every command, acknowledgement, physical effect, and owner override.
- Compare predicted (digital twin) vs measured response; recalibrate models.
- Promote/demote devices between capability levels automatically on evidence.
- Publish a post-drill report after each S4/S5 exercise; findings feed back into the standard (RM-TIP) and the Device Behaviour Matrix.
- Success metrics defined up front: command success rate, time-to-effect, % reverting correctly on dead-man, owner override rate, pressure excursions (target: zero), false-trigger rate, owner trust/opt-out rate.
5. Bidirectional crisis modes
5.1 Mode taxonomy
| Mode | Direction | Typical trigger | Principal actions |
|---|---|---|---|
| R-Restrict | Water down | Drought declaration, zone pressure stress | Pause non-potable irrigation within zone |
| G-Grid | Power down/up | Min-demand or peak emergency | Export curtail, battery dispatch caps, pool pump/hot water shift |
| F-Fire-Prepare | Water up (selective) | Authority-declared fire threat for a polygon | Pre-wet nominated zones (owner opt-in), top up tanks, fill pools/dams where safe, ensure pumps have power |
| F-Fire-Active | Mixed | Fire in or approaching polygon | See 5.2: sequence carefully; potentially stop mesh-driven watering to protect hydrant pressure; protect responders |
| B-Blackout / Island | Power priority | Network de-energised | Prioritise pump + comms + critical loads on battery |
5.2 The central hard problem: "all sprinklers on" can backfire
Turning on every irrigation system at once during a fire can draw down mains pressure exactly when firefighters need it, and pumps need power that may be gone. Therefore the fire modes must be pressure- and supply-aware, not blanket:
- Source-aware tiers: 1. Self-supplied (tank, bore, dam, pool + own pump, battery/solar backed): lowest network risk, first to be activated. 2. Mains-fed: activated only if the utility declares spare capacity for the polygon, in staggered waves, with live pressure feedback and a hard stop.
- Zonal sequencing: wet down the most exposed perimeter/ember-exposed assets first, based on fire spread forecast and consent, not everyone at once.
- Pressure watchdog: if zone pressure drops below the floor, the mesh issues a signed STAND-DOWN for mains-fed devices automatically and instantly.
- Authority control: F-modes are only enabled by the emergency authority (e.g. DFES-equivalent); the utility holds a separate veto over mains draw.
- No promise of protection: owners are told these actions are a supplement to leaving early / their bushfire survival plan.
5.3 Solar and battery dynamics in a fire
Both a resource and a hazard:
Resource - Battery/solar can keep a bore or tank pump, a pressure pump, comms and lighting running when the grid is cut. Pre-position state of charge in F-Fire-Prepare (raise battery reserve; stop exporting; disable arbitrage). - Pump priority in the load hierarchy: raise it above comfort loads.
Hazard / responder safety - Rooftop PV can stay energised in daylight even when the grid is off; responders need predictable isolation. The mesh must never override rapid-shutdown/isolator behaviour or inverter protection. - Batteries can be a fire/thermal-runaway risk; the system should surface battery temperature/alarm data to the owner/authority and honour an authority "isolate PV/battery" signal via the sanctioned paths (DRM0 / utility remote-disconnect / manual isolator guidance), not by unsupported register hacks. - If an inverter/battery is flagged unsafe, the mesh removes it from the optimization and any pump-power plan.
Design rule: in fire modes the Safety Governor priority is: (1) human/responder safety, (2) utility pressure floor, (3) owner consent, (4) property-protection watering, (5) everything else (including the gain-share optimizer, which is disabled).
5.4 Interaction with the solar optimizer (SunVantage)
- Emergency state suspends gain-share optimization and billing is paused for the duration (no commercial gain from a crisis; avoids perverse incentives and reputational risk).
- Optimizer data (SOC, forecast, load) is reused read-only to estimate how long pumps/critical loads can run on battery.
- Regular DER export/curtail logic (G-Grid) uses the same signed message channel as water commands (one trust framework, two resource types).
6. Per-device safe-default matrix (to be filled by the 3.2 programme)
| Device class | On lost heartbeat | Rationale |
|---|---|---|
| Mains-fed irrigation valve | Close (R-Restrict, F via mains) | Protect hydrant pressure |
| Self-supplied fire-prep pump | Continue until TTL, then stop (configurable) | Avoid cutting protection mid-event, but bound tank use |
| Pool pump | Revert to normal schedule | Flexible load |
| Inverter export limit | Revert to normal grid-code behaviour | Never leave in a non-compliant state |
| Battery reserve | Revert to owner's setting after TTL | Avoid indefinite lockout |
Defaults differ by direction and by source; this table is a hypothesis to be tested at S1-S3, not a final spec.
7. Public participation and trust
- Opt-in, tiered consent (advisory only / bounded control / emergency eligible) with clear plain-language disclosure.
- Owner override always wins locally (physical or app), except where it would breach a statutory safety requirement the owner has agreed to.
- Visibility: owners see a log of every command and reason; can leave the programme.
- Equity: tenants, renters, low-income and accessibility needs considered (including people dependent on medical equipment).
- Privacy: minimum data collection; metered data used only for crisis function, retained for a limited time.
- Incentives: rebates or reduced charges, not penalties, in the pilot phases.
8. Governance, legal and risk
| Risk | Mitigation |
|---|---|
| Pressure collapse in fire | Pressure floor, staggering, auto STAND-DOWN, utility veto, self-supplied tier first |
| False sense of security | Messaging, no performance promise, tie to bushfire survival plan |
| Stuck-open valves / flooding / tank drain | Max-duration limits, TTL, offline-behaviour test gate (L3) |
| Responder electrocution / battery fire | Never override rapid shutdown; honour authority isolation; remove unsafe DER from plan |
| Cyber attack triggering mass activation | Signed, geo-scoped, rate-limited commands; human escalation; anomaly detection (see doc 05) |
| Liability | Consent framework, insurer/legal review, statutory backing before S5 |
| Device vendor ToS / firmware changes | Compatibility matrix, local control preferred, vendor partnerships |
| Equity / coercion | Opt-in, incentives, accessible alternatives |
Stakeholders to engage early: DFES-equivalent (fire authority), Water Corporation / local utilities (pressure and hydrant constraints), Western Power / AEMO-aligned network operators (DER rules), local governments, universities, device manufacturers, insurers, community groups.
9. Proposed additions to the funding request (feeds doc 06)
New work packages: - WP-A Device Behaviour Matrix & Conformance Suite (section 3). - WP-B Digital Twin: hydraulics + feeder + devices (S0). - WP-C Staged Pilot & Drill Programme (S1-S4) with success metrics (section 4). - WP-D Fire-mode Safety Case with fire and water authorities (section 5), including DER/responder safety review. - WP-E Community Trust & Consent Design (section 7).
10. Open questions to resolve with experts
- What do fire authorities actually recommend about mains-fed sprinklers during fire danger, and what pressure margins do utilities require?
- Which crisis authority may legally issue F-mode signals, and under what statute?
- How to treat devices that cannot report actuation (open-loop)?
- How do rapid-shutdown, DRM0 and utility remote disconnect interact with a battery-backed pump during fire?
- What minimum pilot size is statistically and operationally meaningful for pressure-impact validation?
- What is the correct default for lost-heartbeat on fire-prep pumps (stop vs continue)?