Historical proposal draft. Preserved working material. Claims of compliance, validation, authority, budget or partnerships in this historical draft are not established by publication. Current plans and evidence limits take precedence. Read current implementation options.

08. Adaptive Testing Bounds & Bidirectional Crisis Modes

RESILIENCE-MESH supplementary scope: learning how real household devices behave, safe rollout limits, and the "opposite" use case (fire: turn systems ON)

Status: DRAFT for review. Not yet audited. Device behaviours, agency policy positions and fire-science claims below are working assumptions to be verified with primary sources (DFES / DWER / Water Corporation / manufacturers) before submission.


1. Why this document exists

Documents 01-06 frame RESILIENCE-MESH mainly as restriction: curtail irrigation and non-essential load in drought or grid stress. Real crises are bidirectional:

Crisis Water side Power / solar side
Severe drought / reservoir stress Reduce non-potable irrigation Reduce peak demand, shift load
Grid stress / minimum demand n/a Curtail export, absorb surplus (load up)
Bushfire approaching Increase wetting of defined zones, if pressure and policy allow Keep pumps powered; manage inverter/battery fire hazards; protect responder safety
Storm / blackout Preserve reserve Island, prioritise critical loads

A framework that can only say "off" is incomplete and, in a fire, potentially harmful. The mesh must carry signed commands in both directions, with the same safety governor, and must learn and bound what each class of household device can actually do before being trusted with either direction.


2. Scope boundary (what the mesh is and is not)

Is: an opt-in, signed, geo-scoped, time-limited coordination layer for non-potable irrigation controllers, pumps, valves, and DER (solar/battery) that already exist at homes, farms and councils.

Is not: - A substitute for evacuation advice, emergency services, or fire authorities' decisions. - A claim that sprinklers will save a home. Evidence on residential sprinkler effectiveness in bushfire is mixed; the mesh must not create false confidence. Participation messaging must say so. - Covert control. All control is consented, logged and visible to the owner.


3. Device Characterisation Programme ("learn how household devices actually work")

Before any rollout, build an empirical device catalogue: how each device class responds to commands, loses connectivity, reboots, and fails.

3.1 Device classes to characterise

  1. Wi-Fi / app hose-tap and garden timers (e.g. Tuya-platform and Gardena-style devices).
  2. Smart irrigation controllers with cloud + local APIs (e.g. Rachio, Hunter Hydrawise, Rain Bird-class products).
  3. Generic Wi-Fi / Zigbee / Matter relays and smart plugs switching pumps or solenoids (e.g. Shelly-class).
  4. Bore/rainwater/tank pumps and pressure controllers (including variable-speed).
  5. Pool pumps (large flexible load, relevant for both water and power).
  6. Solar inverters / batteries (Sungrow, Fronius, GoodWe, Solis, Sigenergy; see the interface research report).
  7. Municipal-scale: council irrigation controllers, SCADA-fed valves.
  8. Legacy "dumb" timers (cannot be controlled; mesh must treat as unmanaged and model their load).

3.2 What to measure for every device model

Attribute Question
Command path Local LAN, cloud-only, BLE, 433 MHz, wired?
Latency Command to physical effect (p50/p95/p99)
Offline behaviour If Wi-Fi/cloud drops mid-run: stays on, stays off, or reverts to schedule? (Critical: a valve stuck open or closed.)
Power-loss behaviour State after brownout/reboot
Schedule precedence Do local schedules, rain delays, or app overrides beat remote commands?
Command acknowledgement Does it confirm actuation, or just accept the message?
Authentication / security Tokens, local auth, firmware update model
Rate limits / ToS API quotas, terms restricting automation
Failure modes Stuck states, duplicate commands, clock drift
Hydraulic effect Flow (L/min), pressure drop at the tap, effect on neighbours
Electrical effect Inrush, running power, interaction with solar/battery

Output: a versioned Device Behaviour Matrix and a conformance test each device must pass to be "mesh-ready at level N".

3.3 Capability levels

Only L3 devices can receive crisis commands. Unknown or failed devices stay L0/L1.


4. Testing Bounds: staged rollout with explicit limits

Each stage has entry criteria, hard bounds, and abort criteria. No stage starts without the previous passing and being signed off by the safety/ethics reviewer.

Stage Environment Max scope Hard bounds Abort / rollback triggers
S0 Simulation Digital twin of a suburb: hydraulics (pressure/flow), electrical feeder, device models from 3.2 Unlimited n/a n/a (learning)
S1 Bench / lab Real devices on a test rig with metered water and mains 1 of each device class Isolated water supply, RCD-protected Any stuck valve, unexpected state
S2 Researcher homes Team's own properties + informed staff ~5-10 sites Owner can override instantly; max run-time per command; non-potable only Any owner complaint, any hydraulic anomaly
S3 Volunteer pilot Informed, consenting households with signed participation terms ~50-200 sites, one distribution zone Pressure floor monitored at zone boundary; command rate capped; TTL <= minutes Zone pressure below floor, device failure rate above threshold, cyber alert
S4 Drill / exercise Scheduled, announced "crisis drill" with utility and emergency services One suburb Drill commands are flagged as drill; real-emergency override always wins Same as S3 + operations centre veto
S5 Regional readiness Multi-suburb, still opt-in Expanded Formal sign-off by utility, emergency authority, regulator Standing abort authority

4.1 Hard bounds that apply everywhere

4.2 Learning loop (how rollout "learns")

  1. Log every command, acknowledgement, physical effect, and owner override.
  2. Compare predicted (digital twin) vs measured response; recalibrate models.
  3. Promote/demote devices between capability levels automatically on evidence.
  4. Publish a post-drill report after each S4/S5 exercise; findings feed back into the standard (RM-TIP) and the Device Behaviour Matrix.
  5. Success metrics defined up front: command success rate, time-to-effect, % reverting correctly on dead-man, owner override rate, pressure excursions (target: zero), false-trigger rate, owner trust/opt-out rate.

5. Bidirectional crisis modes

5.1 Mode taxonomy

Mode Direction Typical trigger Principal actions
R-Restrict Water down Drought declaration, zone pressure stress Pause non-potable irrigation within zone
G-Grid Power down/up Min-demand or peak emergency Export curtail, battery dispatch caps, pool pump/hot water shift
F-Fire-Prepare Water up (selective) Authority-declared fire threat for a polygon Pre-wet nominated zones (owner opt-in), top up tanks, fill pools/dams where safe, ensure pumps have power
F-Fire-Active Mixed Fire in or approaching polygon See 5.2: sequence carefully; potentially stop mesh-driven watering to protect hydrant pressure; protect responders
B-Blackout / Island Power priority Network de-energised Prioritise pump + comms + critical loads on battery

5.2 The central hard problem: "all sprinklers on" can backfire

Turning on every irrigation system at once during a fire can draw down mains pressure exactly when firefighters need it, and pumps need power that may be gone. Therefore the fire modes must be pressure- and supply-aware, not blanket:

5.3 Solar and battery dynamics in a fire

Both a resource and a hazard:

Resource - Battery/solar can keep a bore or tank pump, a pressure pump, comms and lighting running when the grid is cut. Pre-position state of charge in F-Fire-Prepare (raise battery reserve; stop exporting; disable arbitrage). - Pump priority in the load hierarchy: raise it above comfort loads.

Hazard / responder safety - Rooftop PV can stay energised in daylight even when the grid is off; responders need predictable isolation. The mesh must never override rapid-shutdown/isolator behaviour or inverter protection. - Batteries can be a fire/thermal-runaway risk; the system should surface battery temperature/alarm data to the owner/authority and honour an authority "isolate PV/battery" signal via the sanctioned paths (DRM0 / utility remote-disconnect / manual isolator guidance), not by unsupported register hacks. - If an inverter/battery is flagged unsafe, the mesh removes it from the optimization and any pump-power plan.

Design rule: in fire modes the Safety Governor priority is: (1) human/responder safety, (2) utility pressure floor, (3) owner consent, (4) property-protection watering, (5) everything else (including the gain-share optimizer, which is disabled).

5.4 Interaction with the solar optimizer (SunVantage)


6. Per-device safe-default matrix (to be filled by the 3.2 programme)

Device class On lost heartbeat Rationale
Mains-fed irrigation valve Close (R-Restrict, F via mains) Protect hydrant pressure
Self-supplied fire-prep pump Continue until TTL, then stop (configurable) Avoid cutting protection mid-event, but bound tank use
Pool pump Revert to normal schedule Flexible load
Inverter export limit Revert to normal grid-code behaviour Never leave in a non-compliant state
Battery reserve Revert to owner's setting after TTL Avoid indefinite lockout

Defaults differ by direction and by source; this table is a hypothesis to be tested at S1-S3, not a final spec.


7. Public participation and trust


Risk Mitigation
Pressure collapse in fire Pressure floor, staggering, auto STAND-DOWN, utility veto, self-supplied tier first
False sense of security Messaging, no performance promise, tie to bushfire survival plan
Stuck-open valves / flooding / tank drain Max-duration limits, TTL, offline-behaviour test gate (L3)
Responder electrocution / battery fire Never override rapid shutdown; honour authority isolation; remove unsafe DER from plan
Cyber attack triggering mass activation Signed, geo-scoped, rate-limited commands; human escalation; anomaly detection (see doc 05)
Liability Consent framework, insurer/legal review, statutory backing before S5
Device vendor ToS / firmware changes Compatibility matrix, local control preferred, vendor partnerships
Equity / coercion Opt-in, incentives, accessible alternatives

Stakeholders to engage early: DFES-equivalent (fire authority), Water Corporation / local utilities (pressure and hydrant constraints), Western Power / AEMO-aligned network operators (DER rules), local governments, universities, device manufacturers, insurers, community groups.


9. Proposed additions to the funding request (feeds doc 06)

New work packages: - WP-A Device Behaviour Matrix & Conformance Suite (section 3). - WP-B Digital Twin: hydraulics + feeder + devices (S0). - WP-C Staged Pilot & Drill Programme (S1-S4) with success metrics (section 4). - WP-D Fire-mode Safety Case with fire and water authorities (section 5), including DER/responder safety review. - WP-E Community Trust & Consent Design (section 7).


10. Open questions to resolve with experts

  1. What do fire authorities actually recommend about mains-fed sprinklers during fire danger, and what pressure margins do utilities require?
  2. Which crisis authority may legally issue F-mode signals, and under what statute?
  3. How to treat devices that cannot report actuation (open-loop)?
  4. How do rapid-shutdown, DRM0 and utility remote disconnect interact with a battery-backed pump during fire?
  5. What minimum pilot size is statistically and operationally meaningful for pressure-impact validation?
  6. What is the correct default for lost-heartbeat on fire-prep pumps (stop vs continue)?